Pouring concrete is one of the most unforgiving DIY home improvement projects. Unlike painting or framing, where you can easily pause and resume, once concrete is poured, you are on a strict biological countdown before it begins to set. If you underestimate your volume and run out of concrete midway through a pour, you end up with a structurally defective "cold joint." If you over-order, you end up paying disposal fees for concrete you can't use.
In North America, ready-mix concrete suppliers sell concrete by the cubic yard (often simply called a "yard"). One cubic yard is a cube that measures 3 feet by 3 feet by 3 feet, which equals exactly 27 cubic feet.
To calculate the concrete needed for any rectangular slab or trench:
Let's say you're pouring a 12 ft by 20 ft patio slab at a standard 4-inch residential thickness.
In this scenario, you should order 3.5 cubic yards from your local ready-mix supplier.
If you choose to mix your own concrete using premixed dry bags from a home improvement retailer:
For the 12×20 patio above (3.26 cubic yards), mixing by hand would require 147 eighty-pound bags! For any pour exceeding 1 to 1.5 cubic yards, ordering a delivery truck is significantly more cost-effective, uniform, and physically manageable.
Interactive Tool: Use our Concrete Slab Calculator to calculate your exact yardage and subbase requirements in seconds.